A huge amount of work done this week. In the heat that we've had, it is amazing to see. Among the highlights that I could see this morning: the pillars in front of the sanctuary are being erected; pillars going up between the Sanctuary and Youth bldgs to support patio roof; steps installed on risers in rear of sanctuary; drywall is finished in the Pre-school/Kidstown building; and they are starting to install the support framing for the acoustical ceiling tile in the Pre-school/Kidstown bldg.