Saturday, March 26, 2011

03/26/11









Quiet morning at the site. Took many pictures. Contractors have completed pouring the concrete for the front lobby portion of the sanctuary building. Only the sanctuary itself left to pour. They are installing the HVAC ductwork in the Pre-school/Kidstown building. And they have started installing the metal framing over the office spaces at the rear of the sanctuary building. They have also smoothed out alot of the area surrounding the rear of the building. You can accomplish a lot when the rains hold off.

Saturday, March 19, 2011

03/19/11







A beehive of activity today. The contractors are installing metal framing in the Pre-school/Kidstown building. The concrete floor has been poured on the front right third of the main building. The lobby and left front flooring have been prepped for concrete to be poured. And more steel has been hung on the Youth/Genesis building.

Saturday, March 12, 2011

03/12/11














Lots has been done since my visit last week. The slab has been poured for the office spaces. The eaves are being installed around the roof of the Pre-school/Kidstown bldg. Dirt fill has been placed in the frame for the stadium seats at the rear of the sanctuary. And most notable, the steel is being erected for the Youth/Genesis bldg.

Saturday, March 5, 2011

03/05/11
















Quite a bit has been accomplished in the past week, according to what I could see this afternoon. The rebar fencing for the floor has been set in the office spaces. Looks ready for the concrete to be poured soon. And I have included a couple views of the stadium seating area being installed at the back of the sanctuary. It is really starting to look like an actual building. No steel on the Youth/Genesis building site yet.